Interventional Radiology Remodel at the Fargo VA Medical Center

 Located: Fargo, ND VA Hospital

Owner: Dept. of Veterans Affairs

Contract Awarded: October 2016

Project Duration: 9 Months

Project Value: $1,267,525

Contractor Performance Assessment Report System (CPARs)

MDM Construction LLC served as General Contractor for the interior renovation & upgrade project. The Intervention Radiology (I.R) area was completely demolished to the foundation walls and rebuilt. This renovation & upgrade included new offices, exam rooms, testing lab, locker room, bathroom, and equipment rooms. As well as supplying and installing the Radiology equipment. The area received all new walls, flooring, entrances, and finishes. Lastly, the overall square footage and space was increased to accommodate more patents and equipment.

All work under this contract is considered especially sensitive to dust, dirt and noise as the adjacent space remains occupied and functioning during all phases of construction work. MDM Construction LLC is comprehensive of the VA’s desire to continue to provide services to its customers with minimal disruption.